MGC Civil was engaged to deliver a multiple stage civil works package at the Golden Vines Estate, Dayton. Stages 1C & 2C comprised of 39 green title lots.
MGC Civil undertook site clearance, which involved clearing the entirety of the site including the demolition of outbuildings, bulk earthworks with 8,000m3 imported fill. Sewer and water reticulation, stormwater drainage, common trench electrical, gas and communications. Full construction of all asphalt, concrete kerbing and footpaths and retaining walls.
Due to the proximity of the development to the existing POS extra attention to detail for the aesthetics had to be taken with the construction of the retaining walls, stairs and piers as these formed the pedestrian access from the POS to the individual properties.
Client: GM Property Group
Site Area: 15, 000m<sup>2</sup> 39 Green Title Lots
Duration: 14 Weeks